NOTICE OF FINAL SETTLEMENT
In accordance with Wyoming Statute § 16-6-116, notice is hereby given that the Board of Commissioners, Wheatland Irrigation District, Wheatland, Wyoming, the Owner, has accepted from the Contractor,
Rocky Mountain Reclamation
for the project titled
Tunnel Dam Rehabilitation Site Revegetation Project
as having been completed under the terms of the contract dated October 1, 2021. Therefore, on June 13, 2022, the District will release to said Contractor all retainage monies due under the contract. All corporations, firms, or persons having claim against this contract are hereby notified to file claims with the Manager of the District before the above said date, at the address below.
/s/ Daniel Melcher, President
Board of Commissioners
Wheatland Irrigation District
30 West Frontage Road
Wheatland, WY 82201
Public Notice No. 11178. To be published in the Platte County Record - May 4 and 11, 2022.