Public Notice No. 11067

Posted

LEGAL NOTICE

  

NOTICE OF FINAL SETTLEMENT

 

In accordance with Wyoming Statute § 16-6-116, notice is hereby given that the Board of Commissioners, Wheatland Irrigation District, Wheatland, Wyoming, the Owner, has accepted from the Contractor,

Superior Contracting LLC

 

for the project titled

 

Tunnel Dam Temporary Diversion Structure Removal

 

as having been completed under the terms of the contract dated October 1, 2021. Therefore, on December 21, 2021 the District will release to said Contractor all retainage monies due under the contract. All corporations, firms, or persons having claim against this contract are hereby notified to file claims with the Manager of the District before the above said date, at the address below.

 

/s/ Daniel Melcher, President

Board of Commissioners

Wheatland Irrigation District

30 West Frontage Road

Wheatland, WY 82201

Public Notice No. 11067. To be published in the Platte County Record - November 10 and 17, 2021.